C O N D I T I O N S O F S A L E

I- INCLUDED IN OUR OFFER

- Supply of all material as described in our detailed offer.
- Erection and start-up of all our equipment, with the exception of equipment offered on option.
- All pressure pipework between the first and the last structure.
- Complete electrical installation except for the cable trench of the control box.

- Documentation / For each order you will be supplied with the following :

    - Civil Engineering drawings for all purification equipment.
    - General layout drawings of the installation.
    - Operating and maintenance instructions for all equipment supplied.
- Guarantees /
The results of the purification are guaranteed if the process and the dimensions of the equipment are not specified in the client's invitation to tender. All electrical and mechanical equipment is guaranteed for one year from the official completion of all work.

II - EXCLUDED FROM OUR OFFER AND FOR THE CLIENT'S ACCOUNT

- Supplying and connection of waste water to the head works of the installation.
- Evacuation of treated water to the final structure outlet.
- Supply of electrical current to the control box.
- Installation of one or more pressurised water points for cleaning purposes.
- Amenities such as access roads, paths, gardens, orchards, lawns, fencing, gates, lighting etc.
- All earthworks including disposal of excess earth and all ditches and backfill.
- All reinforced concrete works in accordance with our drawings.
- Water and electricity for the duration of work on site.
- Filling the tanks with fresh water before start-up.




© Copyright 2002 - 2007 Hydranet. All rights reserved.